Oceana Residences & Mövenpick Hotel & Spa

Oceana Residences & Mövenpick Hotel & Spa
Dubai
UAE
Project executed by
Envac Middle East
Project status
Ongoing
Keywords
UAE / Residential area

The additional storage capacity of Envac’s system means collection frequency is reduced saving the client money and minimizing the disturbance to residents from waste collection.

This high end residential and hotel development is comprised of over 700 residential apartments and 180 five star hotel rooms.

Envac designed, built and now operates and maintains one Pneumatic Waste Collection System (PWCS) at Oceana.

Envac’s system collects 4 tons of waste per day from the nine residential buildings and hotel and removes it to the collection station located under the hotel. The system has been designed to store up to 3 days of waste thus reducing the frequency of bulk truck collections and reducing the disturbance to residents that all too often accompanies conventional waste collection.

Basic project information
CountryUAE
CityDubai
Project startup2008
In operation since2010
Basic system data
Type of systemStationary Vacuum System
System subtypeSVS 400
Application areaResidential area, Hotel
Design capacity4 tons per day
Area size37,500
Number of fractions1
Number of inlets10
Total metres of pipe900
Type of wasteGeneral waste / Rest